September 12th, 2024 - Guidance on door to door solicitation
Jeffersontown City Hall requires and issues a business license to any company operating within the city limits.
As part of this process each company is informed of what subdivision solicitation is not allowed and Monticello Place is included and these businesses are informed of this information. The HOA expressed concern about the amount of solicitors we saw in the spring of this year and were told that only a few licenses had been issued by City Hall so they were surprised to hear about the number of solicitors. City Hall's recommendation is if a solicitor comes to your house, request to see their "permit" (or business license) which should be from the City of Jeffersontown.
If they do not have a permit, inform them one is required by the City of Jeffersontown and they should not be soliciting in MPCA.
Also, get the name of the business and call City Hall Licensing (502-267-8333 ext 217) to report that particular company.
________________________________________________________________________________________________________________________
Billtown Road Improvements to Begin 4/8/2024 and last until Until Spring of 2025
The following improvements will be constructed throughout the upcoming year:
Easum (turning lanes)
Lovers (turning lanes)
Mary Dell (with school flasher)
Michael Edward (turning lanes)
Fairground (with signal installation)
Vantage Creek (turning lanes)
Colonnades (turning lanes)
Flynn Construction is scheduling to have crews on the project stated above the week of 4/15/2024. The week prior to starting (4/8/2024), Flynn will be onsite to start doing layout/staking for the waterline and casing but will not be in the roadway. Some layout has been completed to date.
The following preparations will begin 4/8/2024
Place Variable Message Boards
Layout and Staking – 4/8 (Crew will not be in the roadway or hindering traffic)
Mobilization – 4/15
Receive Materials – 4/15 and throughout the week
Install Casings (Phases 1-3)
Waterline – 12” Phase 3 (This will commence following the installation of all the casings)
Storm – Phase 3 (This will commence the same time as the waterline of phase 3, with a second crew)
Clearing – TBD, as needed